This application took place in September and October of 2006. All structures of this historical place, called “The Mill Island”, have been renovated with ZINGA, including three footbridges and barriers.These photographs of the structures on the Mill Island, were taken in 2008, 2 years later.
Surface preparation:
➢ Decontamination and Grit-blasting to SA 2 ½ (with blast-furnace slag) and Rz 60 µm
➢ Dedusting with compressed air
Application:
➢ ZINGA: pneumatic spraying in a workshop
➢ ZINGALUFER: pneumatic spraying in a workshop
➢ Local PU Primer Finish: pneumatic spraying on the building site